Updates on Lagoon Perdana (uncompleted units)

Below are the updates (in blue) on Lagoon Perdana (uncompleted units) which I received from the Developer:

Blocks 1, 8 and 3
Waiting for TNB to bring in the equipment by Dec 09. However we are trying to start the preliminary inspections for Blocks 1 & 8 with MPSJ in Nov 2009.

Block 7
We had submitted the revised proposal to MPSJ for planning approval in mid-Sept.

Kementerian Perumahan Dan Kerajaan Tempatan (KPKT) is monitoring this project. I have also spoken to TNB and have urged TNB to ensure there is no further delay. TNB has verified that works for TNB substation should be completed in early December 2009.

11 comments:

YANZ said...

Hi Hannah,

My family owns 2 units there. Thanks for your effort in this burdensome matter.

Keep up the good work, we have faith in you =)

Anonymous said...

thanks hannah. at least this message gives us some hope on the apartment that we'd invested for close to 10 yrs by now. sigh*!

Rajkumar said...

Hi Hannah..
Thanks for the update on Block 7.

Anonymous said...

Hi Hannah,
thanks a lot.
I hope there will be no more delay in the project. Do you have idea what is the best way to raise a flag when there is still attention and help needed ( from you) ? I realize some of the folk in the LP forum are making noise or grumble that were never heard, which I sometimes don't think it is constructive.

lee said...

Dear Hannah,
Thanks a lot for taking the extra mile.

God Bless
F.Lee

Anonymous said...

Dear Hannah,

Thanks a lot for taking the extra mile.

God Bless

Anonymous said...

Hi Hannah,

Thank you very much for the updates!

Regards,
Leon
Block1

nana said...

Dear Hannah,

Thanks for the updates.
Had been a long wait.
Hope that MPSJ will approve the revised proposal a.s.a.p.

Also thank you for your effort.

Khalil. Block 7

nurul said...

Hi Hannah..
Thanks for the update on Block 7.. Hope to hear more from you..

wai said...

Hi Hannah thanks for your effort for the Lagoon Perdana revival.
I heard that the block 8 have a structural defect that is quite serious and that's why until now it's not able tp handover...is that true?

Unknown said...

Hi ,Hannah ,can you please help us to contact the Talam developer regarding Lagoon Perdana Uncompleted block 7 . so far no news from the developer .My son got a unit there level 8 .In 2010 , as he, liked the rest of Block 7 purchasers , opted for refund of the money paid to them since ,Block 7 was not going to be built .As requested by them ,I called up bank to issue redemption ststement to Tenaga Gagah .The bank had done so in April 2011 , issuing the co. 3 months Redemption statement .After that we waited patiently until now .until today no news at all from tenega gagah and we recently got an annual statement from the bank showing that the bank has been continuing charging him monthly interest of almost Rm100 till 1st. of this month . That shows Tenaga Gagah didn't refund the bank the amount that the bank released to them .That means too Their promise to pay us back by 12 instalments what we paid personally also no where in sight .from what I check on line , other block 7 purchersers are also in a fix . What they had written ,some tried to contact T.G. to no avail . We don't have each others contact details except names on the list that T.G . sent to us last time after the court ruling .we don't know who to seek to help us except to write to you again as you had been following up the Lagoon Perdana uncompleted blocks earlier on . Your help is most appreciated by the purchasers of block 7. Thank you